Confidential Site

Confidential Specialty Materials Supplier

SIC installed, relocated, replaced, and modified stacks, piping, and more during an outage.

View inside a specialty material supplier production facility

Value Delivered

This project was completed on time with over 30,000 man-hours on an accelerated schedule during a 60-day outage period at the plant.

Client Objectives

Our client needed mechanical repair services provided on an accelerated schedule.

Solutions

Services we provided for this project include:

  • Installed furnace support steel for the lower melter bed
  • Replaced exhaust stack (required a 350-ton crane)
  • Removed cooler and all associated piping and fans
  • Replaced glass forming line with 24 new units
  • Modified the stack structure
  • Installed a new dilution stack and associated components
  • Relocated and added small utility piping
  • Replaced the circulating piping and process forming level
  • Construction-managed balance of project

Client Background

For over 20 years, we have had a longstanding relationship with this client.