Value Delivered
Southern Industrial Constructors (SIC) installed and commissioned new AS/RS in clean room environments at eight manufacturing locations.
Installation was completed while operations remained in effect and included thorough quality control and assurance documentation, which we turned over to the owner at completion.
We strived for efficient delivery throughout, while still maintaining high quality and safety standards. The average project completion time was two to six months at each location, and all projects were completed with zero safety incidents recorded.
Client Objectives
The client wanted to help improve productivity and material retrieval time and accuracy by installing an AS/RS. SIC also took the owner’s focus on safety and project value to heart and was committed to delivering on both throughout the projects.
Solutions
For the AS/RS at each of the six plants, we provided:
- System layout
- Rigging
- Alignment
- Racking
- Platforms
- Barcode tape
- Shuttle rails and hoists
- Associated electrical installation
Additionally, system startup and commissioning, along with quality control and assurance, were provided to help ensure that the system was operating properly and accurately